Why HVAC RFIs Get Lost (And How To Stop It)
RFIs get lost for a few repeatable reasons: the question never leaves the field as a real RFI, nobody on your side owns it after it's sent, it lives in an email thread instead of a log, it has no due date anyone is watching, and the answer never makes it back to the crew or the drawings. Fix those with one RFI log, a clear owner and due date on every item, a chase schedule, and a step that closes the loop to the field and to change orders.
I handled RFIs for three years at a commercial HVAC firm. The worst ones were never hard technical questions. They were simple questions that sat. A foreman would hit a conflict between a duct run and a beam, tell someone on the phone, and assume it was handled. Two weeks later the crew was still waiting, the install date had moved, and nobody could find who sent what to whom.
Where Do RFIs Actually Get Lost?
In the hand-offs. An RFI passes through four or five people before it's closed, and each hand-off is a chance for it to stall:
- Field to office. A foreman finds the problem. If it stays a phone call or a text, it never becomes an RFI at all.
- Office to GC. Someone writes it up and sends it. If it goes out by email without being logged, nobody else knows it exists.
- GC to design team. The GC forwards it to the engineer or architect. Now it's in someone else's inbox, and your side can't see it.
- Answer back to you. The response comes back, often to one person's email.
- Answer to the field. Someone has to tell the crew, update the drawings and decide whether the answer changes cost or schedule.
Every one of those steps depends on a person remembering. When the office gets busy, which is always, memory is the first thing to go.
Why Doesn't A Shared Inbox Fix It?
Because an inbox tracks messages, not questions. One RFI can turn into a dozen emails: the original, a forward, a clarification, a sketch, a partial answer, a follow-up. Search finds the messages but can't tell you the status. Is it answered? Answered but not sent to the field? Answered with a cost impact nobody priced?
The RFI log is the fix, and most firms already have one. The trouble is that the log gets updated after the fact, if at all, so the log and the inbox disagree. Whichever one is out of date is the one that bites you.
What Should Every RFI Have From The Moment It's Created?
Five things, every time:
- A number and a job. One log, numbered per job, so everyone refers to the same item the same way.
- An owner on your side. One name. That person doesn't have to answer it, but they're responsible for getting it answered.
- A due date. The date you need the answer by to avoid holding up work, not just the date it was sent. Tie it to the install schedule or the equipment order it affects.
- The references. Drawing sheet, spec section, photos from the field, and any related RFIs or submittals.
- The impact if it isn't answered. Which crew, which area, which order. This is what makes people move.
If an RFI goes out without an owner and a needed-by date, it's already halfway to lost.
How Should RFIs Get From The Field To The Office?
Make it easier for a foreman to send a proper question than to make a phone call. A short form on their phone works: job, location, what they found, a photo, and how soon they need an answer. That goes straight into the log as a draft, and the office turns it into a formal RFI.
The point isn't paperwork for the field. It's that the question is captured the moment it's found, with the photo, before the details are forgotten.
How Do I Keep RFIs From Going Quiet After They're Sent?
Chase on a schedule, not on memory. A simple rhythm works:
- A reminder to the GC a few days before the needed-by date.
- A second follow-up on the due date, copying whoever the GC's process says to copy.
- A flag to your PM the moment it's overdue, with the work it's holding up.
Track the turnaround so you can see patterns:
RFI turnaround = date answered − date submitted
Look at it by GC and by design team. If one engineer's office takes much longer than the others, that's something to plan around in the schedule and raise in the next coordination meeting, with dates to back it up.
What Happens After The Answer Comes Back?
This is the step that gets skipped most. An RFI isn't done when the answer arrives. It's done when:
- The field has it. The crew that asked knows the answer and has the sketch or revised detail.
- The drawings reflect it. Whoever maintains your working set marks it up, so the next person doesn't ask the same question.
- Cost and schedule are checked. If the answer adds work, it needs a change order. If it moves dates, the schedule needs to know.
That third point is where the money is. An RFI answer that adds a reroute, a bigger unit or extra controls work is a change order waiting to be written. If nobody connects the RFI to a change order, your crew does the extra work and your company eats it.
Can Software Or AI Fix This?
Partly. Software can do the remembering: log every RFI the moment it's created, attach the photo and drawing reference, set the due date, send the chase emails on schedule, and flag anything overdue. AI is good at the reading part: pulling the relevant spec section, finding earlier RFIs on the same job about the same system, and drafting a clear question from a foreman's rough notes.
What it shouldn't do is answer technical questions or send things to a GC on its own. An authorized person on your team reviews every RFI before it goes out and decides what an answer means for cost. The system prepares the work so that person spends their time on judgment, not on digging through email.
If your RFIs live in inboxes today, the free audit is where I'd look first: how a question moves from the field to the GC and back on your jobs, and where it's stalling.
Frequently Asked Questions
Who should own an RFI on a mechanical contractor's side?
Usually the project manager or project engineer on that job. They don't have to write the answer, but one named person is responsible for getting it answered by the needed-by date and getting the answer back to the field.
What's the difference between an RFI and a change order?
An RFI asks a question about the design or the documents. A change order changes the contract scope, price or time. Many RFI answers create a change order, so every answered RFI should be checked for cost and schedule impact.
How do I measure if our RFI process is getting better?
Track RFI turnaround (date answered minus date submitted) and the number of RFIs past their needed-by date, by job and by GC. Check the overdue list weekly.
Find The First Workflow Worth Fixing.
Book a free audit. We look at how this work moves through your company today and tell you what we'd build first.
Book a Free AuditFree Audit Call · We only take on 6–7 new builds a month
Built by the team behind BuiltByLa. Owned by you.